dc.description.abstract | This study sought to establish the determinants of effective monitoring and evaluation of County
government funded infrastructural projects. The term effective is used to mean whether the
project monitoring and evaluation has or can achieve its objectives. The study identified three
independent variables which included staff technical skills, budgetary allocation and stakeholder
participation. Not only does best practise require that projects are monitored for control but also
project stakeholders require transparency, accountability for resource use and impact, good
project performance and to benefit future projects. Therefore the study shed insight on the
aforementioned benefits. The study was carried out using descriptive survey research design
which entailed both qualitative and quantitative data collection procedures. The study was
carried out within Nakuru East constituency which is located within Nakuru County and as such
a beneficiary of county funds for infrastructure projects; the elected members of county assembly
(MCA), resident engineer and the residents of this formed the target population. There are 157,
167 residents, one resident engineer and five elected members of county assembly from this a
random sample of 387 residents was sought for the study out of which 341 respondents
participated. Also, a census study was done for the resident engineer and the MCAs. The study
employed questionnaire interview format as its primary data collection method. There were two
kinds of questionnaires; one for the technical team which include the MCAs and resident
engineers and the other for the stakeholders. Two research assistants were identified and trained
on research tools and procedures. The primary data collected was edited, coded and organised
into manageable summaries whereby both qualitative and quantitative data analysis techniques
were used using Statistical Package for Social Science(SPSS). Quantitative data collected was
analyzed, presented and interpreted using both descriptive statistics while thematic analysis
techniques was used to analyze qualitative data collected in the open ended questions. Linear
regression analysis was used to establish the relation between independent variables and
dependent variables; the regression equation was Y= 1.311+0.349X1 + 0.405X2 + 0.69X3. The
regression equation indicated that taking all the three variables at zero, effectiveness of
monitoring and evaluation was1.311. According to the findings it was concluded that all the
three variables were significant (p<0.05). The study is intended to inform both the county and
national government of effectiveness of monitoring and evaluations of infrastructure projects
funded by county and play a vital role in strategic planning for county infrastructure
development. | en_US |